A3 problem-solving sheet: Deviation in roast level of Arabica blend coffee beans

Themenportal · ausschließlich ansehen. Keine Anmeldung, Bearbeitung, Speicherung oder KI-Nutzung.

A3 report for root cause analysis of over-roasting: burner control, sensor timeout, 6W, Ishikawa and temperature curve verification.

A3 AI Tool

Public example · read-only

41 %

Problem solving sheet

Team lead: Markus Weber
Team members: Sarah Klein, Thomas Schmidt

Facts / team building

ProblemCoffee roast too dark – roast level deviates by +8 Agtron from target
PlantNorth Plant
Area/workstationRoastery
Product/componentArabica Blend coffee beans 500g
Number of defectsRoast level above target value, burnt bean surface
Date discoveredQuality control after roasting process
Discovered byRoastery Shift Supervisor
Recurrence ja× no
Sketch or photo for problem description

Fehlerklassifizierung

Nicht ausgewählt

Problem description

DescriptionThe problem is
(NOK product/process)
The problem is not
(Comparison with an OK product/process)
What exactly is the problem?Arabica Blend coffee beans with roast level above target and burnt surfaceOther coffee varieties or roasts within the target range
Wo does the problem occur?North Plant, Roastery DepartmentStorage area or packaging line
How is the problem evident?Visual inspection and colorimetric measurement (Agtron scale)Customer Notification
Wann does the problem occur?Directly after the roasting process in quality controlDuring raw material delivery
Why is it a problem?Actual roast degree exceeds defined quality specificationsIntended taste adjustment

Containment actions

Nr.ActionResponsibilityDeadlineStatus
1Quarantine and blocking of the affected batch (Arabica Blend) in the North Plant storage areaSarah Klein14.10.26●
2Manual visual inspection and color measurement of all stored roasting batchesThomas Schmidt15.10.26●

Root cause analysis (Ishikawa)

Human
  • Mangelnde Überwachung des Röstkurvenverlaufs am Leitstand
Machine
  • Brenner-Modulationsventil klemmt bei 85 % Öffnung
Material
  • Rohkaffeefeuchte lag bei 9,8 % statt 11,5 % (schnellere Röstung)
  • Röstprofil-Abschaltautomatik im SPS-Programm deaktiviert
Method
  • Abluftkamin wies Rußablagerungen auf (geringerer Zug)
Environment
  • Thermoelement Rösttrommel seit 8 Monaten nicht kalibriert
Measurement
Problem:
Coffee roast too dark – roast level deviates by +8 Agtron from target
Probable causeTo be reviewedNicht priorisiert / ausgeschlossen

Root cause analysis (5-Why)

Root cause 1
Burner did not switch to partial load in time
1. Warum?Why were the beans over-roasted? Because the roasting temperature was 18 °C above target in the last 90 seconds.
2. Warum?Why did the temperature exceed the target? Because the gas burner continued to run at full load.
3. Warum?Why did the burner not modulate down? Because the analog control valve was mechanically jammed.
4. Warum?Why did the control valve jam? Because dirt particles in the gas filter were not cleaned in time.
5. Warum?Why was the cleaning missing? Because the maintenance interval for the gas filter was not stored in SAP PM (root cause).
Grundursache:Missing preventive maintenance plan for gas filter and modulation valve.

Actions to eliminate the identified root cause(s)

Nr.ActionResponsibilityDeadlineStatus
1Replace modulation valve and replace gas filter with double-chamber filter with differential pressure monitoringMaintenance25.10.26◐
2PLC safety shutdown: Automatic burner stop for roasting curve deviation > 5 °CAutomation28.10.26○

Effectiveness evidence (testing, trials, KPI monitoring)

Nr.ActionResponsibilityDeadlineStatus
1Roast level over 30 consecutive roasting batches within target Agtron 55 ± 2Sarah Klein20.11.26○

Validation of the successful solution (FMEA, Control Plan, instructions, training)

Nr.ActionResponsibilityDeadlineStatus
1Create maintenance plan in SAP PM for all roasting ovens (cycle: 4 weeks)Head of Maintenance15.11.26○

Transfer to other products/processes (Lessons Learned)

Nr.Proposal / activityResponsibilityDeadline
1Retrofit differential pressure monitoring on ovens 2 and 3Maintenance15.12.26
Justification for non-necessitySame burner type on roasting lines 2 and 3 at the North plant.

Completion

The problem-solving case must be presented by the team leader to the steering committee and confirmed by them. This simultaneously serves to relieve the team leader.
Thermal protection and PLC shutdown successfully validated. All roasting batches within the target range.
Completed on
18.10.26
Markus Weber
Team lead
Dr. K. Wagner
Control loop member
○ Action with deadline and responsible person◐ Action being implemented● Action implemented● Effectiveness verified